Destruction, demolition and new construction

Sometimes, you have to strip away the old before you can build the new. That’s our theme this week, as we bring you dramatic photos of the latest demolition and construction in Hale Library.

A map illustrates 10 of K-State's university buildings. with Hale Library located at the center. A small red mark is at Hale's upper left corner.

To help give you a sense of the site of our first photos, the jagged red spot above marks the location of the fire.

Two peaked plywood roofs stand about four feet high in the foreground. An attic-like space is situated on a ledge above and behind them.

Today, if you enter Historic Farrell Library’s third floor and stand on the false floor built on top of the scaffolding that fills the Great Room, like Associate Dean Mike Haddock did recently, you can see that spot.

The Great Room murals are covered by the plywood boxes with peaked roofs, which you see in the photo above. The attic space where the fire burned is directly above and behind them. In an attic-like space, a charred wall is at the right. The floor is missing except for some support beams, so you can see through to the room below.

Up close, you can see that the debris has been cleared away. Through the holes in the attic floor you look down into the Academic Learning Center (ALC) where the student athletes met for study tables. ALC staff members were the ones who first smelled the smoke, even before the fire alarms went off.

While the charred walls are a clear mark of the destruction, this also serves to illustrate that the actual fire was contained to one location. The vast majority of the damage was from smoke and water.

But enough destruction for today’s post.

How about some demolition? In Hale Library as we knew it, there were a lot of stairwells–many of them in tucked-away corners of the building that weren’t highly trafficked. They took up prime real estate, so in our renovation, we’re reclaiming the stairway highlighted in purple above.

A pile of rubble sits at the base of a metal staircase.

Before we can renovate, though, it has to be demolished. It might not look very innovative right now, but workers have jack-hammered away concrete to clear away space for the Innovation Center on Hale Library’s first and second floors.At the left, a worker in a blue hardhat stands on a staircase. A shower of sparks rains down from the next flight of stairs on the right.

After the concrete was hauled out, crews used blowtorches to disassemble the frames of the metal staircases.

A stairwell made of concrete blocks stands nearly empty except for a small piece of metal stairway and a section of red scaffolding.

Here you can see that the demolition has cleared out the stairs between third and fourth floor. As of today, that entire stairwell has been emptied. Progress!

A computer-generated rendering shows a dozen students scattered around a large room that features tables and chairs of different styles, computer screens, white boards, and a tool board hung with tools in a makerspace setting.
In the Innovation Center, users will generate virtual reality experiences through 360-degree video or 3-D animation. They will create artificial intelligence, edit audio and video and learn to use state-of-the-art technology that is not readily available elsewhere on campus.

So, Associate Dean Mike Haddock (who takes 97% of the amazing photos we bring you) is back. The map below shows the northwest corner of the first floor. Mike, as represented by the small purple man, is standing in Historic Farrell Library’s Room 117, and the rectangles highlighted in pink represent shafts (called “chases,” in construction parlance) that extend
through the building from the first floor up to the fourth.

A line drawing of the upper left portion of a floor map. Four small pink rectangles are in a horizontal row across the top third of the map.

This is what Mike sees when he turns and faces east-north-east toward Willard Hall and Mid-Campus Drive. A large, shabby room lined with glass windows with small square panes and columns with ornate plaster moldings.

If he turns to face south, he sees a wall of Room 117 opposite the large bank of windows looks like this:

A very thick, worn wall made of limestone and plaster is different shades of white and beige and has several different-sized rectangular windows and doorways.For most of us, the exciting part of construction comes when you get to look at the shiny, clean end product. We’re not there yet, but there’s really important work going on now so that the new Hale Library’s infrastructure can support all of those shiny, clean new spaces, like the previously mentioned Innovation Center.

Case in point regarding infrastructure: The steel beam over the doorway in the photo above is new reinforcement.

A rough limestone wall is at right. Two narrow rectangular-shaped holes are cut in the floor in front of the wall. Dust and stone debris coats the rest of the floor.If we were to walk through that doorway, you’d find the chases that are highlighted in pink on the floor plan above. On second, third and fourth floors, guardrails have been built around those chases for safety, since they’re essentially like an open elevator shaft.

A room with a lot of exposed metal wall framing is filled with give large rectangular metal pieces of ductwork wrapped in metallic silver insulation.

Over the last month, workers have been installing ductwork wrapped in insulation into those chases. The ductwork runs through the building from top to bottom.

A length of metallic silver insulation-wrapped rectangular ductwork is installed in one of the chases in front of the limestone wall.

This is just some of the construction work on Hale Library’s infrastructure. With improvements like these in place, the building will have improved air quality and more efficient heating and cooling.

A worn limestone and plaster wall in shades of off-white and white is punctuated by several rectangular windows and door. Several of those spaces are now blocked by the air vents wrapped in metallic silver ductwork.

Progress is happening. It’s not shiny and clean, but it’s important work that will take us one step forward to our new Hale Library.

As always, if you have questions about the process, please comment on the blog post or contact us at libcomm@ksu.edu!

To all of our student and faculty readers, happy spring break! We won’t be posting next week, but we’ll be back on March 19.

Hale Library update from PGAV architects

On Feb. 13, 2019, architects from PGAV joined K-State Libraries all-staff meeting to discuss next steps for the Hale Library renovation.

Four people stand in a cluster in discussion at the front of a classroom with white walls.
IT coordinator Renee Gates, architects Pat Duff and Jennifer Goeke and Dean Lori Goetsch confer following the February all-staff meeting.

The key take-away: Construction on most of the first floor has been scheduled. Meanwhile, designs for floors two through five are under development.

So in relation to the graphic above, we are at the end of Stage 3 when it comes to the first floor, and between Stages 1 and 2 for the other floors of the building.

A man stands with a microphone at the front a room. At right a PowerPoint slide is projected on the wall.
Mike Schaadt of PGAV architects gives Libraries employees an update at the February meeting.

Who are the architects in charge of this process? PGAV is based in Prairie Village, Kan., and they’ve worked on the design of more than 25 libraries, archives and special collections facilities in the last several decades.

In their work on Hale Library, PGAV has helped establish this timeline for target reopening dates:

  • Portions of first floor: Fall 2019
  • Second and fifth floor: Spring 2020
  • Third and fourth floors: Fall 2020
  • Historic Farrell Library, all floors: Late 2020/early 2021

Note that Farrell Library, the 1927 portion of the building that includes the Great Room, will open last: The plaster walls are still wet, and plaster dries very slowly. The process can’t be rushed if the integrity of the material is going to remain intact. The historic conservation of the Great Room murals and the woodwork is also very complicated.

But rest assured that the new Hale Library will incorporate the things that K-State students ask for most. We’ve spent nine months in concert with PGAV and the university community to develop spaces that fill a wide variety of needs.

Here are just a few of those desires as expressed by K-State students:

A man stands at right. A graphic purple background to his left says "Quiet study is good, but it doesn't have to be absolutely silent. A table with a lot of space is important. I like to spread out."

For years, noise complaints have been one of the top issues reported to the Hale Library Help Desk. Third floor was the quiet floor, but because of the way sound traveled through the building, it was never truly quiet.

Now we have the opportunity to rezone Hale Library’s noise levels: In the renovated building, first and second floors will be the most active and bustling. Third floor will be quiet, with some talking allowed, while fourth floor will be the place to go for really intense quiet. That means students like Nick might want to try a big table on third floor for an optimal study experience.

One of Hale Library’s amenities that students say they miss most since the fire is the white boards. They were always in high demand—which also meant we had to replace them frequently.

In the new building, students like Erin will have plenty of white board options to choose from. In fact, Hale Library will have entire walls covered in white boards, including long stretches on first and second floor. Those walls will be punctuated by strips of limestone that offer a glimpse of the 1955 addition’s exterior that was covered in subsequent expansions.

A group of three students sits in the lower left in front of a graphic purple background with two quotes: "I like windows and natural light," and "We definitely need outlets."

Hale Library spaces were repurposed multiple times over the years. In the most recent iteration, the first and second floors of Historic Farrell Library housed collections and office cubicles. That meant that the larger K-State community rarely had the opportunity to appreciate the gorgeous natural light and architectural details in those spaces.

In the renovated 1927 building, the first and second floors will be converted into public gathering spots featuring some of our high-use collections like juvenile literature. They will also be outfitted with plenty of soft seating and tables so students like Carlie can study in a room flooded with natural light.

Another retrofit: When the 1997 Hale Library renovation occurred, no one could have predicted how high the demand for outlets would be 30 years later: Today’s students want to charge their laptops and phones while studying. Since the entire building has to be rewired, we will be able to increase the number of outlets in Hale Library exponentially!

A man stands at right in front of a graphic purple background with a quote that reads, "I'd like to see smaller rooms for smaller group sessions."

First-year students like Jacob haven’t ever experienced Hale Library. When it reopens, one of the major new improvements will be the reservable rooms that will accommodate groups of all sizes.

In fact, the first floor, which reopens in fall 2019, will feature at least a dozen of these spaces, and more will be spread throughout the building. Students will finally have a private spot equipped with video technology to practice presentations, conduct interviews and meet with study groups.

These are just a few of the types of improvements we’ve been planning with PGAV, and we look forward to featuring progress on construction of these spaces in the coming months.

 

 

A floor-by-floor progress update

At our recent all staff meeting, Associate Dean Mike Haddock gave the K-State Libraries team a run-down on the latest happenings inside Hale Library. So, as we’re lining up at the starting line for our massive first floor renovation project this spring, we wanted to give you an idea of where things stand.

Starting on the ground floor: The first floor is finally clean, so the plastic  sheeting that divided the space into sections has left the building. Now, first floor looks…. a lot like the other big, empty, clean expanses on second, third and fourth floors.

There’s a little more action on the ground floor of the 1927 portion of Hale Library, where crews are removing sea foam green paint from the plaster work. 

Removing the paint will aid in drying the plaster, which is still retaining moisture from the water that poured through Historic Farrell Library during the fire.

This space, Room 117, used to be packed with a lot of shelving, and except for a small group of devotees who flocked to the dozen or so tables that lined the room, few people knew about it. Once it’s renovated, Room 117 will be home to our juvenile literature and curriculum materials collections plus plenty of comfortable seating. More people than ever will be able to enjoy its beautiful architectural details and natural light.

Up in the “Harry Potter Room” on third floor, a lot of carpentry wizardry has gone into building protective boxes around the Great Room murals. This will prevent damage during all of the renovation that has to happen in the space.

Above, you can see protective dark felt fabric stretched across the murals, and on top of that, a layer of plastic.

Once the plywood “rooms” around the murals were complete, they fastened small doors at multiple levels up and down the height of each painting so the workers can climb up and down the scaffolding and check on each mural’s  condition on a regular basis.

This photo is of the “dance floor” which is supported by the scaffolding that fills the Great Room. The dance floor gives workers access to the underside of the roof. Recently, a lot of the wood supports criss-crossing the space were removed.

Next, workers reinforced the existing metal roof supports with steel beams. It’s exciting to see improvements like these going in to strengthen the building so it will be here for many more generations of K-Staters.

Now, if you were to jump into the photo above, climb the orange ladder from the dance floor, go up through the attic and exit the little portal to the right, you’d arrive on the roof of Hale Library.

There used to be some massive air handling units out here on the roof, but those were heavily damaged by the fire and removed with a crane last summer. Now, a new penthouse is going up.

Before you think that we’re building something super fancy, we learned that in construction, “penthouse” refers to a shed-like structure built on the roof to house machinery or provide roof access, not “a luxurious dwelling on the top floor.”

Nonetheless, this new home for our HVAC systems will be the nexus for improved heating and cooling across the entire 550,000-square-foot building. Students who have spent time in Hale Library during the heat of summer and cold of winter (and during those hot-cold-hot fluctuations in spring and fall) have heard us say how difficult it was to control temperatures in the massive space. This penthouse and its equipment will make the new Hale Library dramatically more comfortable!

So, from the first floor to the roof, that’s what’s new at Hale Library. Our renovation begins in earnest very soon, and at this point, we still aim to reopen an amazing first floor space in fall 2019.

In the meantime, we leave you with a discovery Haddock made when he was in Hale Library to take these photos.

Nothing like a little dark humor to brighten up a cold winter day.

Our final list of study locations for finals week (finally)

Finals week is next week! Since Hale Library is temporarily out of commission, we wanted to highlight some study locations that might make things less stressful during this very stressful time of year.

The full list of hours, dates and locations can be found at the Libraries website, but to give you an inside look, my coworkers and I did a quick tour of a few lesser-known study spaces. The following buildings were not highlighted in our beginning-of-semester post about study spots, which featured a massive picture of my head that still haunts me.

All of these spaces are reserved for quiet study, which is the hardest to come by on campus during finals week.

The Alumni Center was our first stop.

My coworker Rebekah, a senior in public relations and K-State Libraries student employee, shows off the space in the Alumni Center Ballroom on the first floor. 

In addition to setting up their massive space with tables and chairs, they have several small meeting rooms (just ask at the front desk about availability). The Alumni Center will also serve free coffee 8-10 a.m. on Monday and Tuesday (while supplies last).

The KSU Foundation at 1800 Kimball Avenue is offering up their enormous conference room on the main floor. Two perks: It’s right next door to Bluestem Grille, and it’s on the aTa Bus line (Office Park/Grain Campus stop).

Avery, senior in political science and philosophy and KSU Foundation student employee, poses in their enormous conference room. This is one of the few spaces on our list of study spots that has great natural light.

Students looking for space that’s open all night should head to the K-State Student Union. In addition to the usual Union study spots, they’ll have their ballroom set up for studiers; that area will stay open until midnight.

Emma, sophomore in marketing and K-State Libraries student employee, being a good sport for this blog post.

Holtz Hall will be open from 9 p.m. to 2 a.m. Sundays through Thursdays, and they offer two dozen study rooms. The Berney Family Welcome Center has twenty-three study rooms that would be great for small groups of two to four; they’re free from 8 a.m. to 11 p.m. Monday through Thursday (check at the welcome desk for availability).

“If I really needed total silence, I would hustle to grab one of the small rooms in Holtz Hall or the Berney Family Welcome Center,” Rebekah said. “The other spaces will accommodate a ton of people, so they’ll have more ambient noise. I think the ballrooms would work perfectly well, though, especially if I had my headphones on.”

Nine of the twenty-three small meeting rooms in the Berney Family Welcome Center.

“We highlighted spaces that aren’t usually available for studying because people won’t be as aware of them,” Emma said. “Two of my go-to spots that aren’t on this list are the Business Building (because I spend so much time there anyway) and the tucked-away seating areas in the Rec Center. If you’re someone who really needs to get a stress-relieving workout in, that would be a great spot.”

Again, we have a guide online that outlines dates, hours, and details about these study spaces and many, many more (21 in all)! We hope these will help lessen student stress, even though finals week will remind us all again how much we miss Hale Library.

Watch, read and wear all things Hale Library!

Maybe it’s the coming holiday season, but we’re feeling reflective. Join us in looking back at our post-fire Hale Library progress via some exciting releases (video, print, and apparel) that you might have missed.

WATCH

We are so excited about this KSU Foundation video that was presented at the Friends of the K-State Libraries gala. It includes some intense live footage that hasn’t been seen widely.

Hale Library: A Next Generation Library from KSU Foundation on Vimeo.

We love the part where Roberta Johnson says, “When we’re done, we’re going to be better. That’s the only way you can look at losing this much. Eighty percent of the building has been destroyed. You can’t not feel devastated by that unless you have the hope that … when you put it back together [it’s] going to be better.”

That’s exactly what keeps us excited about coming to work every day and creating the news you read about Hale Library!

READ

Speaking of reading, if you’d like a more in-depth version of what’s happened in the last six months, we hope you didn’t miss “Unexpected Journey,” in the most recent K-State Libraries Magazine.

Two issues of K-State Libraries Magazine, one open and one closed, lie on a wooden surface. Both feature photos of firefighters outside Hale Library during a fire.
When we were planning this issue last spring, we didn’t think we’d feature firefighters on the cover.

An overwhelming amount of work has occurred since May. This is a great place to get a recap, view photos not seen elsewhere and take in some inside points-of-view from our administrators and faculty.

WEAR

Finally, if you’re looking for the perfect gift for someone in your life who loves comfort, K-State and all things purple, consider the Hale Library t-shirt. On campus, it’s available at the Library Help Desk in the K-State Student Union, or you can order it online via the K-State Super Store. Proceeds go to the Help for Hale fund, which will assist with renovation efforts.

In closing, here are a few of our favorite photos of our friends in their Hale tees:

Willie the Wildcat 💜
Librarians from USD 383 and the Manhattan Public Library. (They surprised us with this photo, and it still makes us tear up a little.)
K-State Libraries student employees, from left to right: Patrick Dittamo, Skyler Gilbert, Hawa Dembele, Carleigh Whitman and Andrew Le.

Cleaning house: Week eighteen update

We’ve witnessed a lot of things go down on the fourth floor of Hale Library over the years: students camping under tables with blankets and pillows during finals week; physical anthropology study sessions that featured skeletons and piles of bones; and, well, let’s be honest, we’ve seen some fourth-floor stacks activities we wish we hadn’t.

But we’ve never seen fourth floor as a woodworking shop … until now. A lot of materials — like the entire physical library collection and one of the murals — have been packed out so they can be cleaned and stored until Hale Library renovations are complete.

Dozens of unvarnished, clean wooden beams of different shapes are arrayed on the floor.
Clean wooden beams from the Great Room ceiling fill Hale Library’s fourth floor. 

The Great Room woodwork is staying, though. Crews are cleaning and stripping the beams. Eventually, they’ll be refinished, and when the roof and ceiling are repaired and the space is ready for renovation, the beams will be reinstalled.

The fourth floor woodworking space is walled off with plastic.

Two workers wearing white t-shirts and hard hats stand next to heavy pieces of wood resting on sawhorses.Crew members from John Canning Co. clean and remove varnish from two decorative arch braces that hung in the Great Room. 

A dark-haired man in a white t-shirt and hardhat uses a cloth to wipe a heavy piece of wood sitting on sawhorses.
A worker from John Canning Co. cleans a piece of Great Room woodwork.
Another worker applies stripper to remove coats of old varnish.

Meanwhile, back in the Great Room, conservators continue to monitor and stabilize the David Hicks Overmyer murals.

At left, a worker in a white hard hat stands elevated on a rough wood floor supported by scaffolding. An allegorical mural depicting the arts is to his right.
John Canning staff members have cleaned the murals, removed the damaged layer of varnish, stabilized areas of paint and applied a new layer of varnish.
In a close-up, shadowy view, a woman in a white hard hat and yellow construction best holds an iPad. The handle of a mallet is visible tucked under her right arm.
Julia Manglitz, an architect from TreanorHL Historic Preservation, stands on one of the ledges supported by scaffolding in the Great Room. She explained to us how she tests the condition of the plaster by “sounding,” or tapping the wall with a mallet and listening for how hollow it seems.
A woman's torso and arms are visible; she holds an iPad with a line drawing of the Great Room wall on it in her left hand and points at it with a stylus in her right hand.
Once she’s tested the plaster through sounding, Manglitz creates a visual map of the condition of the wall on her iPad. She reports that many sections are still very wet. (In fact, on the two floors below the Great Room, the moisture level in some of the plaster and stone walls is as high as 80 percent.)
An art deco style painting of a figure with curling brown hair
A figure from the “Arts” mural is covered in white spots of thermoplastic adhesive, which is used to stabilize flaking paint. 

Additional mural restoration is on hold until two things happen: First, the plaster walls need to be more thoroughly dried out, and second, the rest of the Great Room restoration needs to be more advanced so that the murals aren’t re-damaged during that process.

In a room filled with scaffolding, large rectangles of gray fabric cover the murals on the wall. To prevent the murals from getting damaged while the rest of the Great Room is renovated, conservators have covered them with a felt-like fabric that’s attached to a tack strip that runs around the perimeter of each painting.

In the temporary “dance floor” space above the murals (which are barely visible at right), the roof joists are exposed. 

Up above the murals, the Great Room’s decorative woodwork has been removed, and the ceiling has been completely torn out. Crews from Hutton Construction are moving in to start replacing the roof and ceiling in the 1927 building.

Elsewhere in Hale Library, most of the recent action has centered on cleaning toxic soot from all surfaces and scraping up the carpet glue. Since that process is nearly complete, the size of the Belfor Property Restoration crew has been scaled down.

Metal scaffolding extends down a four-story stairwell.
Your daily dose of vertigo is brought to you by the scaffolding in Hale Library’s southeast stairwell, where they recently cleaned walls, railings, light fixtures and the ceilings.
Eight workers in hard hats and yellow construction vests are stationed across the entire length of the floor wielding long-handled scraping tools.
The process of scraping carpet glue on Hale Library’s third floor was a lot labor intensive and a little gross and sticky.  
Library or roller rink? After the glue was scraped off, the concrete and tile floors were cleaned and polished.

Even though the Belfor folks are starting to leave Manhattan, they aren’t taking a break: As organizations across the Carolinas assess the devastation wrought by Hurricane Florence, Belfor will be on the ground with their massive semi-truck command center and their amazing people. We wish them a safe assignment as they begin recovery efforts there.

It’s been eighteen weeks of damage assessment and drying out, packing collections and planning. The space is a clean slate, and in forthcoming posts we’ll be able share a lot more about the Hale Library of the future.

Week Fifteen Update: A ton of Jenga fun and other developments

Librarians are pretty obsessive about tracking everything in their collections. It’s all meticulously cataloged, which allows us to identify where each item is at any given point in time, who has it, and when it’s coming back.

Cataloguing pieces of a mural? The oak beams from the Great Room? A 50-pound solid oak acorn finial? That’s a little out of our wheelhouse.

The wooden acorn finials (shown on the cart at right wrapped in a green protective covering) weigh 50 pounds each.

Fortunately, John Canning Company is in charge of disassembling Historic Farrell Library so it can be put back together better than ever. We’re confident that there will be no Humpty Dumpty situations on their watch.

Let’s set the scene: There’s a coupla big ol’ holes in Farrell Library. Charred, scary holes that have been covered by a temporary roof.

Until recently, it was difficult to get up close and personal with the ceiling to photograph the fire damage.

Below that, you have the dance floor. That’s what they call the temporary plywood floor built on top of the metal scaffolding that fills the entire Great Room. We don’t want to keep those holes, so the dance floor gives workers access to the ceiling where they can begin the process of removing the fire debris to replace the ceiling and roof.

Wooden beams that will be preserved are laid out on the “dance floor.” Every piece is labeled so that once the room has been renovated, it will be possible to reassemble the woodwork.

Workers are carefully taking down the woodwork that lends the Great Room much of its historic character. It’s a little like high-stakes Jenga: Removing, labeling and relocating each piece of wood is a delicate process.

In order to keep the ceiling repair process moving forward, workers have to take each piece of wood off of the dance floor. Here you can see the scaffolding that supports the floor. 

When Farrell Library is sporting a new ceiling and roof sans holes, it will be time to reverse-Jenga all of that woodwork. We can’t wait to see it back where it belongs!

The ceiling has been removed already in this portion of the Great Room, and the rest of the beams will follow.

Over in the Richard L. D. & Marjorie J. Morse Department of Special Collections, librarians have been going hands-on to pack out the Libraries’ unique research collections and rare materials. This area of the building mainly experienced smoke damage, and we initially hoped the books and other holdings could be cleaned on site. It’s become clear, though, that in order to keep them safe, everything needs to be transported to secure, reliably conditioned space.

“We should have everything out before the end of September,” said Associate Dean of Libraries Mike Haddock. “It’s been a slow process, but we can finally see the light at the end of the tunnel.”

Only a few rooms of special collections materials remain in Hale Library. They’re the last of more than 1.5 million items to leave the building and go into storage where they will be professionally cleaned.

The remaining special collections materials will join the 140,000 boxes that have already been sent to one of the three offsite storage facilities we’ve contracted to keep everything safe. The newest location in our stable of stables is one of Underground Archive & Storage’s facilities, a former limestone mine in Kansas City, Mo.

Underground Archive & Storage has facilities across the region; the one we’re using occupies a series of caves created by limestone mining. Given that Hale Library is a massive limestone construction, we think there’s a metaphor here. We’ll let you know when we figure it out.

Now, it might not have been the first thing on everyone’s mind after the fire, but we had materials on order that arrived over the summer. We were a little busy, and we weren’t able to make those available … until now!

NEW K-State Libraries materials that were destined for Hale Library are being held in Seaton Hall. You can visit Library Help in the Union and ask for the item you want in person; we’ll retrieve it on the spot. Alternately, you can make your request through our website and specify which library help desk you’d like to pick your item up at.

And, as we look to the future, we continue our work with the architects from PGAV. They recently completed “like-for-like drawings”: PGAV determined what the building looked like right before the fire. Now those drawings go to a contractor who assigns what the replacement costs would be if we were to rebuild Hale Library as it was. These are essential steps that have to happen before the various parties involved assign a dollar amount to the total damages. Only after that is completed will we know how much K-State will receive from the insurance companies.

A group of six librarians and architects sit and stand around a table as one of them points to a print out of a floor plan.
While we wait for information about total damages and insurance, staff are working with PGAV to imagine a library for K-State’s future.

Until then, if you ever have questions you’d like us to address in this blog, please comment below or contact us at libcomm@ksu.edu.

And to everyone who has been following along with us on this journey, thank you! Your comments and words of encouragement mean the world to us!

Week Ten Building Update

Since our last update, we’ve been hard at work creating a blank canvas on which to build our new Hale Library. Crews have removed a huge variety of items from the building, including entire rooms full of shelving components and a one-ton air conditioning unit.

Inside the building

Most of the books have been removed from the first floor, with the exception of a small portion of Stack A. Once all the books are removed from a space, crews start dismantling shelving units.

Several white metal bookshelves are lined up behind each other, exposing an empty room.
Here, only the shelving framework remains after the shelves were removed. Note the imprint of the books left behind in the soot at the bottom of this photo. July 25, 2018.
White metal bookends and shelves lay in stacks on the ground.
Metal bookends and pieces of shelving units piled on the floor of Room 117, which is the ground floor of the 1927 building. July 25, 2018.  

Crews are removing compact shelving from the third and the fourth floors, too. The majority of bookshelves are unsalvageable due to smoke and water damage.

An empty green room with pallets on the floor and tools scattered on the floor.
Room 117 was tightly packed with movable shelving units. It was an out-of-the-way study space that students valued for its isolation and beautiful natural light. July 25, 2018.

Recently we found mold growing in the wood display cases by the second floor entrance, so they had to be removed. Previously, the display cases featured rotating exhibits that highlighted the Libraries’ services and collections.

A large wooden cabinet display is being deconstructed by workers.
The cabinets next to the entrance have been dismantled. July 31, 2018.

Lead abatement has been completed in Room 212, the second floor of the 1927 building. Before the fire, this space was filled with cubicles that were occupied by iTAC employees. Large swaths of the walls are now bare of paint, which will help the plaster dry more quickly.

Room 212 a few days after the lead abatement. July 31, 2018.

HVAC Removal

Three massive heating, ventilation and air conditioning (HVAC) units on the roof that were close to the source of the fire were deemed not salvageable, so they had to be removed.

A large crane extends up past a five store limestone building.
Since the largest of the units was about eight feet tall and eighteen feet long, we brought in a crane to do the job. July 26, 2018.
The metal arm of the crane extends high above the tan, peaked roof of the library as it lifts a large, rectangular piece of the HVAC unit.
The largest unit was cut into three pieces to make it easier to lift off of the roof safely. July 26, 2018.

When the pieces were on the ground, Jeremy Sharp, a K-State facilities program manager, noticed that pieces of the aluminum had melted from the fire. To inflict that kind of damage, the heat would have needed to reach 1100 degrees Fahrenheit.

Two men stand next to a large metal rectangle unit and one man stands inside of the unit that is just as tall as he is.
The units are tall enough that grown men are able to stand inside of them comfortably. July 26, 2018.

Renovation

We are now in the early stages of meeting with PGAV, an architecture firm that is working on both damage assessment and the plans to renovate Hale Library. There is still a long road before we will be able to reopen, but it is an exciting time to start planning for the future.

A group of people sit around a table with blueprint on them.
Lori Goetsch, Dean of Libraries, and other library staffers meet with architects from PGAV, the firm that is helping with the renovation. July 19, 2018.
A group of people sit around a table with blueprints and a blonde woman is extending her arm to a blueprint to point at something.
Library employees share how they used the old Hale Library, what they loved about it and what they would change. July 19, 2018. 

We are still in the initial stages, but this gives us all a glimpse of what’s to come.

Week seven update: Special collections, the Great Room and more

Welcome to our week seven Hale Library update!

Now that most floors of the building are emptied and we’re starting to work with a blank slate, truly dramatic changes are less visible. Nonetheless, surprises crop up on a regular basis—some less welcome than others.

Near a Great Room sign on Hale Library's third floor, yellow construction lights are strung across the ceiling.
Since this photo of the third floor was taken, the rest of the books have been boxed up and moved to Executive Court. June 28, 2018. 

Special Collections

The vast majority of the materials from the Richard L. D. and Marjorie J. Morse Department of Special Collections are located on Stack G and Stack H. For weeks, our plan was to clean those materials on the premises.

“We really hoped we could set up cleaning stations in the building and go through the process of vacuuming them and wiping them down to remove soot right here on site,” Roberta Johnson, director of administrative and IT services, said.

Unfortunately, Stack G is getting hotter: A water line that provides cool water to the chilling system was damaged in the fire. It needs to be fixed, but that water line is an area of the Great Room that is currently inaccessible.

This week, we received the news that temperatures in Stack H are rising, too.

Rows of metal shelving draped in plastic are lit up by a flashlight.
There aren’t any lights in Stack H, and temperatures are rising; materials there will be boxed up and moved offsite soon. July 6, 2018.

“All of the building except the data center in the basement and a few elevators are still powered by generators,” she added. “The cooling system for Stack H isn’t getting reliable power, and until good commercial power is available, and the unit’s electrical issues are resolved, these problems will continue.”

So the materials in both Stack H and Stack G will be packed out soon and transferred to Executive Court, the storage and cleaning facility near the airport.

“In some places, the building conditions are getting worse instead of better,” Johnson said. “We just can’t risk leaving valuable materials in non-climate controlled space.”

The Great Room

A construction worker kneels on a platform at the top of the scaffolding.
A worker erects scaffolding near the ceiling along the south wall of the Great Room. June 28, 2018.

Additional scaffolding has been constructed in the Great Room. Once complete, crews will build a floor across the top; from that floor they will be able to reach the ceiling and start the restoration process.

Large plastic tubes and metal scaffolding are back lit by a leaded glass window in the Great Room.
The dehumidifer tubes are still removing moisture from the Great Room, and a second set of tubes is pumping chilled air in. July 2, 2018.

Julia Manglitz, a professional art restorer, is on-site to oversee efforts to preserve the Great Room murals, which were painted by David Hicks Overmyer in 1934.

“Her goal is to dry the plaster out very slowly in order to cause the least possible damage to the murals,” Haddock said.

An agricultural worker holding a scythe is framed by metal scaffolding in the foreground.
A detail of the agriculture mural. June 28, 2108.

He also explained that she is using a large black light to examine and photograph the murals because the UV light can make damage on the painting’s surface readily visible.

The “We are the Dream” mural is in the Academic Learning Center, which is on the opposite side of the wall from the Great Room Mural. Manglitz hopes to remove the “We are the Dream” canvas from the wall as the plaster dries, but that painting is in less-than-ideal condition and the outcome is uncertain.

“We are the Dream.” July 2, 2018.

In a related effort, there is a full painting crew in the Academic Learning Center, but they are actually “unpainting,” or removing the paint from the walls, thereby erasing a barrier that is preventing the plaster from drying out.

The next step will be to remove the ceiling in the Academic Learning Center, another part of the effort to eliminate moisture from the environment.

One building challenge and one bit of trivia

Meanwhile, up on the roof, there are three very large, non-functioning air conditioning units that will have to come off. (Well, two very large ones, and one very, very large one.)

Three rectangular gray metal boxes sit on the library roof.
Three air conditioner units are nonfunctioning. The unit at right is approximately 10 feet high by 18 feet long. July 2, 2018.

“It’s a challenge we haven’t quite managed to come up with a workable solution for yet,” Mike Haddock, associate dean, said. “There’s been talk of everything from dismantling them and bringing them down in pieces to airlifting them off with a helicopter.”

Stay tuned for those photos, right?

About a month ago, we shared photos of the dehumidification tubes that prompted references to science fiction pop culture.

Well, sci fi fans, meet the hydroxyl generator.

A large box with a circle at its center is lit by four smaller glowing blue lights inside.
A hydroxyl generator casts an eerie glow. July 2, 2018.

There are multiple boxes emitting an eerie blue glow across fifth floor. These hydroxyl generators use a phenomenon that occurs in nature to neutralize odor left by the fire.

Hydroxyls are molecules that are created when sun’s ultraviolet rays react with water vapor in the air; however, they don’t occur indoors. The generator creates atmospheric hydroxyls that neutralize smells by breaking down the chemical bonds in the odor-causing bacteria molecules. Hydroxyls also neutralize some molecules in mildew and in mold spores. The machines are safe for use in occupied areas.

Hale Library: Week six update

Today marks six weeks since the fire at Hale Library. Since last week, carpet has been completely removed from several floors, more of the drop ceiling system has been taken out, scaffolding has started going up in the Great Room and crews have begun the labor-intensive process of wiping soot from every surface in every room.

As you’ll see here, the some of the changes are quite obvious!

The Great Room

The Great Room was the area that received the most damage from the fire, and it will take the longest to restore. In perhaps the most visually dramatic change, scaffolding is being constructed throughout so that crews can access the walls and ceiling and start the cleaning and restoration process.

Workers constructing scaffolding in the Great Room.
In these photos, the scaffolding lines the walls, but eventually it will fill the entire space so workers can access the ceiling, too. June 28, 2018. (Click photo to enlarge.)

The murals are on plaster walls that are still drying out, and we are working with preservationists in order to save them.

Workers construcing scaffolding along the murals in the Great Room.
Scaffolding on the south wall against the murals. June 28, 2018.
The Great Room ceiling: At left, a wooden beam that extends across the space has split lengthwise. At right, green mold spreading across the white plaster.
Scaffolding will allow workers to access the Great Room ceiling, which warped and split one of the wood beams and caused mold on the ceiling. June 28, 2018.

The First and Second Floors

If you read our five-week update, you know that most of floors have been cleared of furniture, carpet and drop ceilings.

As of this week, the first and second floors are completely empty. It’s exciting to see a blank canvas emerging. Now the area can be cleaned, and we can start thinking about its future.

Dozens of students on the second floor of Hale Library study and use the computers and printers.
The second floor before the fire.
Second floor of Hale Library after the carpet and ceiling tiles were torn out.
The second floor on June 6 before the furniture, technology, ceiling grid and lights were removed.
The second floor on June 28, 2018, after the carpet, furniture, technology, drop ceiling system and some areas of drywall were removed.
Hundreds of cardboard boxes sitting on the concrete floor are stacked four high.
During the initial push to remove furniture and books from Hale Library, the first floor was used for storage. June 11, 2018. 
First floor of Hale Library with ceiling, carpet and furniture removed.
Now, first floor has been cleared of all furniture and boxes. It is empty and ready for thorough cleaning. June 28, 2018.

Isolated Mold Outbreak in the Stacks

The library is a 550,000-square-foot building, and most of it is still without commercial power, which means that many of our inspections have been conducted with flashlights.

Of course, we are always looking for emerging problems throughout the building, even in places where we initially thought the damage was minimal. However, we now know that lack of light prevented us from identifying one area of concern.

In the last week, we found mold in a small, isolated section of the stacks.

A close-up of mold blooming across the tops of several books.
A small section of books has been affected by a mold outbreak. June 26, 2018.
Mold blooms across the fore-edge of several books sitting on metal shelving.
A small section of books has been affected by a mold outbreak. June 26, 2018.

So what happened? As the hundreds of thousands of gallons of water that permeated the building during the fire drained from the top floors to the bottom, it flowed along any unrestricted path available. Initially, the stacks were dry, but some of that water drained down the edges of a pipe. Since there is a gap around the pipe where it passed through each floor, water seeped through to the levels below. As the water progressed down the exterior surface of the pipe, books in the immediate vicinity got wet.

Red pipe passes through a hole cut in the drywall ceiling.
Pipe that passes through several levels of the stacks. June 26, 2018.

Since this discovery, we have removed the affected books. We remain vigilant for similar leaks and pockets of moisture throughout the stacks.

Packing and Removing Books

Since the last update, we continue to remove books from the library for cleaning at an offsite location. Currently, crews are boxing and moving books on the third and fourth floors.

As of July 2, crews have packed more than 38,000 boxes of books and library materials.

Until June 28, the elevators were operating thanks to power from generators, but the elevators still didn’t have lights, so crews were moving books from the upper floors to the ground floor in the dark.

Rows of empty white metal shelving units.
Empty shelves on the third floor that were once filled with books. June 28, 2018.
Boxes of books are pushed on carts to be removed from Hale for cleaning.
Belfor workers help load out boxes of books from Hale’s fourth floor for cleaning. June 28, 2018.

Cleaning Fifth Floor

The fifth floor was relatively unscathed, but it still needs to be professionally cleaned to remediate soot and smoke damage. Even ductwork will be cleaned throughout the entire building.

On fifth, crews are cleaning every accessible surface that was exposed to soot and smoke. It’s a very labor-intensive process. First they vacuum all surfaces—walls, windows, doors, everything—with a HEPA vacuum, which is a vacuum affixed with a filter that can capture particles of 0.3 microns with 99.97% efficiency. Next, the crew goes over everything again with dry chemical sponges. And finally, they wipe the surfaces down with clean washrags.

This process will be repeated on every surface throughout the entire building.

A circular room without ceiling tiles with only ceiling grids and duct work exposed.
The fifth floor hemisphere room with ceiling tiles gone, exposing duct work in the ceiling. 

In the fifth floor, ceiling tiles have been removed, which makes the ductwork accessible for the cleaning crew.

A women with a yellow vest stands on a ladder vacuuming the metal grids on the ceiling.
A crew member HEPA vacuums near the ceiling before sponge cleaning.

All surfaces are cleaned with HEPA vacuums before they are wiped down with chemical sponges.

A women in a yellow vest holds a long pole with a chemical sponge to clean the inside of the ceiling and duct work.
A crew member uses a chemical sponge to wipe down the ceiling and duct work.

In order to reach every inch of the soot with a chemical sponge, the crews put them on long poles.

Two black trash bags sit next to each other. In the left bag are dirty yellow chemical sponges and in the right bag are brown dirty wash rags.
Used chemical sponges and rags have to be disposed of.

Emptying damaged furniture, construction materials and books from the library is part of the process of creating a clean slate. Day-to-day, sometimes it feels like a slow process that requires an overwhelming amount of labor. When we think about the big picture, though, it’s an exciting first step toward renovating Hale Library and creating a new, vibrant research environment that will serve the entire K-State community.

We’re taking a break for the rest of the week, but check back early next week for the latest Hale Library news! Have a fantastic Independence Day, all!

After the Fire: Where are they now?

After the Hale Library fire, more than 80 K-State Libraries faculty and staff members plus 37 Information Technology Services staff members and several dozen student employees were left without office space. After the first few days of assessing damage to the library, it became clear that Hale wouldn’t reopen for some time.   

Thanks to the generosity, assistance and compassion of our K-State community, we have been able to find temporary office locations across campus. We are so appreciative to the Alumni Center, Bluemont Hall, Business Building, Dykstra Hall, Seaton Hall, Unger Complex and Welcome/Career Center for their generosity in welcoming us into their spaces. 

Our employees may be spread across campus, but they are ready to provide their help and services to campus and community once again.

(Please note, these photos represent only about half of the K-State Libraries and IT Services employees. Dozens of library staff members have worked shifts in Hale Library helping to pack damaged books and remove them from the building. Some were in meetings when we visited, and still others refuse to let us get within 50 yards when we have a camera out.)

Academic services librarians for humanities, fine arts, social sciences, business, education and instructional design are located in 2001 Business Building.
The Center for the Advancement of Digital Scholarship and the STEM librarians are in 2123 Business Building (NSSI).
The K-State Libraries admin team, including Dean Lori Goetsch, are on the third floor of the Alumni Center.
Special collections staff members are located in 116 Bluemont, but special collections faculty members do not yet have a long-term location.
Communications and marketing, web services, and planning and assessment are in office spaces in the Berney Family Welcome Center.
Building services, represented here by Jesica Thornton, is working out of 217 Dykstra. (We will get your photo yet, Robin Brown!)
The Unger Complex is home to the largest number of Hale Library employees. More than 20 members of the acquisitions department, the metadata, preservation, and digital initiatives department and the content development department are all in 200 Unger Tower.
Half of the Libraries’ information technology services staff is located in 146 Unger.
Three additional information technology services employees can be found in Seaton Hall … or, more frequently, on the move, supporting their coworkers in all of the various office spaces across campus!
Library user services is located in 3002 Seaton.
Interlibrary services is operating out of the Library Annex near the Manhattan Regional Airport.
Most IT Services employees can be found in the Cat’s Pause Lounge in the K-State Union. Additional staff members have been relocated to 2116 Business Building and to Unger Complex.

Hale Library: Week five update

Today marks five weeks since the May 22 fire at Hale Library. In this update, we have a lot to share about our demolition progress.

A huge amount of damaged drop ceiling, drywall and carpet has been removed.

Ceilings

Ceiling grid and tiles are caving in after suffering water damage.
Second floor, Media Development Center, May 31, before ceiling removal.
Ceiling tiles and grids are removed from a hallway, exposing pipes and electric wiring.
Second floor after ceiling tiles were removed, June 14.
A room with ceiling grids up without ceiling tiles, leaving the tubes and electric exposed, while the furniture is covered in white plastic.
Second floor after ceiling tiles were removed, June 8.
Ceiling grids have been removed from the library and tubes and wiring are even more exposed, while furniture is covered in white plastic.
Second floor of Hale Library with all ceiling grids removed, June 14.

Walls

There was also extensive water damage to the drywall. In some areas, only a few feet needed to be removed, but in other parts, the entire wall had to be demolished and only metal studs remain.

Yellow wall with spray paint marking two feet of wall needing to be removed, while two feet of the wall has been removed, exposing metal studs.
Second floor, June 14. Two feet of the wall was removed since only the lower portion was damaged
Dry wall has been removed, leaving only metal studs in its wake and exposing a wall sign for the Center for the Advancement of Digital Scholarship.
First floor, June 8. In the Center for the Advancement of Digital Scholarship (CADS), half to all of the drywall was removed.
A hallway has all of the carpet, ceiling tiles, and try wall removed, leaving only metal studs and cement flooring.
First floor, northwest corner, looking east down the hallway that runs between Room 117 and Stack A, June 14. The majority of the drywall was removed from this portion of the building.
A room with debris over the floor and a single light in the middle of the room shows a wall with only metal studs and no dry wall.
Fourth floor, Academic Learning Center, June 14. The ALC is the on-campus tutoring facility for student athletes; this space experienced extensive damage and will be gutted.
A stairwell is caution taped off with the side wall exposing metal studs and electric wiring.
Fourth floor, north stairwell, June 14.
Dry wall has been removed showing a limestone wall behind metal studs.
Second floor, June 14. When drywall was removed, limestone from the exterior of the 1955 Farrell Library addition was exposed.
Looking through a metal chainlink fence lays brown baseboards next to purple dumpsters.
Baseboards were water damaged and will be disposed of along with the drywall and drop ceiling system.

Furniture and technology: Soot damage

Most of the furniture in the building was damaged beyond repair and will need to be thrown away. The tables that were located across all five floors of the building suffered so much smoke damage that the toxic soot cannot be cleaned off of them.

Already, the majority of the furniture from the first through the third floors has been disposed of. All told, it filled a large industrial dumpster 65 times.

Because the soot from the smoke is so toxic, every inch of ductwork in the 550,000-square-foot building will need to be taken down and professionally cleaned.

In addition to the ductwork, all surfaces of every room will have to be professionally cleaned to eliminate the soot. Cleaning the first through fourth floors could take about ten weeks.

Blue topped tables sitting in a row next to each other.
The tables sustained a significant amount of smoke damage. Most have been disposed of.
A mouse has been moved on a blue desk to reveal a light blue outline of the mouse.
When loose items that were left on the tables were picked up and moved, it was easy to see how much soot coated all surfaces throughout the building.

Furniture: Water damage

The original Farrell library tables suffered intense water damage that stripped and warped the wood beyond repair. These photos were taken two days after the May 22 fire.

A grey capital has fallen on a water damaged table.
The Great Room tables sustained a significant amount of water damage.
Brown wood tables are warped and wavy after severe water damage.
Both the veneer and the underlying wood was cracked and warped from prolonged exposure to water.

Book Retrieval

Luckily, not everything was completely unsalvageable. While removing books, the crew and staff were in desperate need of book carts and were able to salvage 30 book carts from the fifth floor.

Progress continues on the book retrieval process. At this point, 30,000 full boxes of books have been removed.

Rows of colorful book carts are lined up against the wall.
Book carts, fifth floor, June 14.
Rows of deconstructed cardboard boxes are lined up against the wall from floor to ceiling.
This is just a small percentage of the boxes that are ready to be assembled and packed with books that will be relocated relocated offsite for cleaning and storage.
On the right are cleared off white bookshelves and on the left the wall is lined with brown cardboard boxes.
The entirety of the Music and Art collection has been boxed and moved off of the fourth floor.

Technology

In the last week, the data center, which had been operating off of generators, was returned to commercial power.

Additionally, the electronics in the building have been assessed, and about 70 percent of what was deemed a loss has been prepared for disposal through the e-waste process.

Dozens of computer screens sit on a concrete floor.
Damaged computers waiting for the e-waste process.

Obviously, there are many moving parts to the recovery process. Before we can implement our plans for K-State’s future Hale Library, the damaged portions of the building must cleared out. We are making strides forward every day.

We’d like to extend our deep appreciation to our K-State Libraries and Information Technology coworkers and the Belfor team for everything they’ve accomplished thus far.

 

 

After the Hale Library Fire: What’s past is prologue

It started shortly after 4 p.m. on Tuesday, May 22.

Alarms went off in Hale Library. Employees reported smoke.

The building was safely evacuated, and emergency personnel from the Manhattan Fire Department, Riley County EMS, Fort Riley, Blue Township and others responded.

Firefighters on the roof of Hale Library.
Manhattan firefighters on the roof of Hale Library as the sun sets on May 22, 2018. Photo courtesy Manhattan Fire Department.

In order to save the structure, several hundred thousands of gallons of water flooded the building.

Outside of the library, the entire K-State community experienced system outages. To protect the university’s data center, which is located in Hale Library’s basement, online tools such as Webmail, HRIS, KSIS and others were taken offline. By June 4 —thanks to efforts from staff from multiple units across the university who worked round-the-clock—vital services were restored due to generator power.

Additionally, since the majority of the university’s library materials were unavailable, the Libraries made it a priority to restore interlibrary loan services as soon as possible. They were up and working again by June 1.

This is what K-State’s faculty, staff, and students experienced outside of Hale Library.

Inside of Hale Library, the damage was much, much worse than initially hoped. On May 24, President Richard Myers and Dean of K-State Libraries Lori Goetsch saw the destruction for the first time.

Dean Goetsch examines the damage.
Dean Lori Goetsch uses the flashlight on her cell phone to point out an outline left in the soot after wet books were removed from Room 117.

“To be honest it was pretty devastating,” Dean Goetsch told Brady Baumann of KMAN. “It was heartbreaking to see the amount of damage. In order to enter the library, we of course put on hard hats. We had to put boots on because the water was up to our ankles. … It was really sad. You know, I’ve been here for 14 years, and Hale … feels like home. … And it was like seeing your home damaged.”

Historic Farrell Library bore the worst of the destruction. Holes for the firefighting efforts were cut in the roof, and a lot of the water poured through that part of the building.

A stained glass window is reflected off of the standing water on the Great Room's floor.
The condition of the Great Room on May 24, 2018, two days after the fire.

Many K-Staters are familiar with Farrell Library’s iconic Great Room, but most are probably not aware that the 1927 building also houses the Academic Learning Center (ALC), K-State’s athletic tutoring facility. The ALC is an essential study location that provides vital tutoring services for student athletes.

The “We Have a Dream” mural, which was created 1978-80 by several multicultural student organizations, covers one large wall of the facility. The ALC will have to be gutted, and it is uncertain if the mural can be saved.

The “We Are the Dream” mural is draped in plastic sheeting while drywall removal is conducted in the ALC.

Below the ALC and Great Room, on Farrell Library’s second floor, the IT Help Desk, multiple iTAC offices and the Media Development Center were extensively damaged, as was the technology in those spaces.

Nevertheless, even as K-State Libraries administrators were absorbing the scope of the disaster, they were also launching the recovery process.

Within 48 hours, Belfor, an international disaster recovery and property restoration company, was on site to assess the damage.

On May 27, more than 75 Belfor workers began removing wet carpet and ceiling tiles from the library. By June 1, their ranks had grown to nearly 200 workers from eight states. They swarmed the site, performing assessment, cleaning and determining what could and could not be salvaged.

Walls of technology spaces have been taken down to the studs.
The ceiling tiles and the majority of the drywall in the Media Development Center on Hale Library’s second floor has been removed.

Most of the carpet and ceiling tiles in the building have been removed, and it’s estimated that about half of the drywall will need to come out.

Two weeks following the fire, all of Hale Library’s occupants—87 K-State Libraries faculty and staff members, 38 IT Services staff members, 2 Academic Learning Center employees and dozens of student employees— were generously welcomed into 13 temporary locations across the university.

Many, many challenges lie ahead for the recovery effort. Even today, there is very little lighting since electricity has not been restored. The generators on the lawn power dehumidifiers and air cooling units in an attempt to keep the temperature and humidity more manageable. On hot days, it reaches 90 degrees inside the building. Workers have to wear hardhats, vests, and respirator masks, so that combination makes the heat even more oppressive. The sheer scale of the recovery for the 550,000-square-foot Hale Library is immense, and there are new problems to be solved at every turn.

Some of the tubing that helps remove moisture from the building is piped out of the windows by the entrance to Hale Library’s main floor.

This blog will be our place to share our journey, and we hope you’ll follow along as we plan for the future.

The outpouring of support from faculty, staff, students, alumni, donors and other libraries around the country has been overwhelming. We are profoundly grateful for their generosity and kind words, and we know that with the K-State Family behind us, the long chapter ahead of us has a very, very bright ending for an exciting, new Hale Library.