Building update: Jumping into July

As we jump into July, a lot of changes are coming to Hale Library. Besides the continuation of construction and progress on the building, the library will also welcome the public back for the first time since early March.

Starting July 1, the second floor of Hale Library will be open to visitors. Patrons must wear a mask or facial covering and practice social distancing while in the building. Services offered include access to the help desks, course reserves and computers. Extra steps will also be taken to promote safety and keep the environment clean. You can learn more about the reopening at our continuation of services page.

While the second floor will open to the public, the remaining floors continue to undergo a vigorous and rapid transformation.

In Joyce and Joe’s Cornerstone Café, the tile behind the counters was installed, and the fireplace was completed.

A picture of the fireplace inside the cafe.
The “flames” in the fireplace do not produce any heat, but they do change colors and will provide a comfy atmosphere. Safety first!
A picture of the faux marble counter in the cafe.
Behind the cafe’s front counter, tile was added in a geometric design.

The Sunderland Foundation Innovation Lab is undergoing more plaster work and drywall installation. The specific rooms for equipment and varying labs are starting to take shape—it’s only a matter of time until we can start moving in some tech!

This picture shows the view from the middle of the first floor of the Innovation Lab, looking toward the entrance to Historic Farrell Library.
This picture shows the view from the middle of the first floor of the Innovation Lab, looking toward the entrance to Historic Farrell Library.

In the Great Room, the protective boxes have been removed from the murals so that workers can perform plaster work around the edges. Removal of the boxes will also allow art restoration professionals to begin work on the murals later this fall.

A picture of the west end of the Great Room.
The view of the west end of the Great Room from the fourth floor balcony is fantastic! On the left hand side, you can see one of the decorative columns that span throughout the room.
A picture of the covered murals.
The murals are still covered to protect them while the crew continues plaster work around the edges.

The Virginia Carlson Family Reading Room will house the juvenile literature and curriculum materials collections. Virginia Carlson was a graduate of Kansas State College in 1952, a librarian and teacher. Virginia’s family has studied in Hale Library for more than four generations and they have invested in the building to honor her legacy. We are extremely grateful for their generosity!

A picture of the Virginia Carlson entrance.
A new entrance into the Virginia Carlson Family Reading Room is under construction.
A picture of the wall ornament in Historic Farrell Library.
During construction and plaster work in Historic Farrell Library, several interesting architectural details have become more noticeable. Here, you can see a wall ornament on the first floor.
A picture of a crew member working on a lift outside the library.
Late last month, crew members also worked on fixing the seals on several external windows in the building. It’s good to make sure that the cool air stays in during these warm summer days!